06 — Twelve-week setup

Implementation roadmap

Setup and commissioning across twelve weeks, starting with legal and site validation.

Programme timeline

Workstream123456789101112
Legal + site survey
Design + quotations
Construction + services
Fit-out + systems
Commissioning + training

Phase deliverables

Weeks 1–2

Confirm legal model, member count, dimensions, water, power and greenhouse footprint.

Weeks 3–4

Issue room layout, electrical load schedule, HVAC heat-load, security plan and three comparable quotes.

Weeks 5–10

Complete envelope, drainage, electrical, partitions, climate, water, access and fire systems.

Weeks 11–12

Run empty-room tests, verify alarms, balance airflow, train members and issue certificates.