07–09 — Operating framework

Governance and controls

Role boundaries, records, risk controls and the action register that must close before any plants enter the facility.

Roles

RoleResponsibility boundary
Member custodianControls, tends, harvests and stores only their assigned plants.
Site stewardManages access, building safety and shared infrastructure only.
Compliance secretaryMaintains adult IDs, allocations, access logs and incident register.
Safety officerFire, first aid, evacuation, water leaks and equipment isolation.
Professional contractorsElectrical, HVAC, security and fire maintenance under controlled access.

Minimum document pack

  • Legal opinion and association constitution
  • Member ID, consent and plot-use agreement
  • Bay, plot, plant and key register
  • Access, visitor and contractor register
  • Electrical CoC, fire plan and evacuation map
  • Cleaning, hygiene and pest-monitoring records
  • Incident, loss, waste and emergency register
  • Maintenance, calibration and commissioning records

Top risks and controls

RiskLevelPrimary control
Member model challengedHighWritten current legal opinion; no outsourcing or product-linked fees.
Electrical overload or fireHighEngineered DB, dedicated circuits, CoC, detection and isolation.
Heat or humidity failureHighRedundant cooling, alarms, maintenance and emergency response.
Unauthorised accessHighIndividual locks, controlled entry, CCTV and audit trail.
Budget overrunMediumThree quotes, fixed scope, staged approvals and 15% contingency.

Action register — what happens next

  1. 01Appoint a South African cannabis lawyer and confirm the operative private-use rules.
  2. 02Confirm 25 named adult members and whether each will personally tend plants on site.
  3. 03Measure the indoor room: length, width, clear height, doors, windows and drains.
  4. 04Confirm electrical supply: phase, amperage, transformer limits and outage history.
  5. 05Confirm water source, pressure, storage and a potability / suitability test.
  6. 06Survey greenhouse dimensions, orientation, wind exposure, slope and access.
  7. 07Commission electrical, HVAC, fire and security concept designs.
  8. 08Obtain three comparable quotations against one issued scope of work.
  9. 09Approve budget, member contributions and contingency before ordering.
  10. 10Commission the facility empty and close all defects before operation.

Information needed for version 2

Farm town / province
Indoor dimensions / height
Power supply / backup
Water source / test
Greenhouse dimensions
Confirmed member count
Available capital budget
Target construction month

Legal references

Start with legal and technical validation. Do not purchase lighting before the connected-load and heat-load studies are complete — the systems must be engineered as one package.